That is possible, maybe.  We have a written procedure for field testing in explicit detail, which, if followed by the UT tech, will provide us the necessary data in a format enabling us to produce a more informative piping assessment report.  However, virtually all past efforts have failed due to the raw data provided being inaccurate, due to other requirements of our procedure not being followed, or to other flaws or omissions in the information provided.  In the event we are able to work with a local UT company to assist with interpretation of data, CorrView International would not be held liable toward the accuracy of UT measurements or report.